| June 1990 |
Vision of development first appears |
| June 1998 |
LinksLiving considers role as project developer |
| March 2000 |
Planning submission lodged |
| August 2000 |
Planning approval granted |
| March 2002 |
North golf course construction commences |
| October 2002 |
Recycled water contract signed with Earthtech and Melbourne Water |
| January 2003 |
Stage 1 (Legends Release) completed |
| February 2003 |
Display Village Opens |
| March 2003 |
First house construction commences in Stage 1 |
| April 2003 |
Stage 2 (Federations Release) completed |
| June 2003 |
Stage 4 (Redgums Release) completed |
| August 2003 |
$12 million Clubhouse construction commences |
| June 2004 |
North golf course opens for play |
| July 2004 |
Official grand opening of clubhouse |
| August 2004 |
Stage 3 (Sandhurst Island) completed |
| September 2004 |
Stage 5 (Fairway Views) completed |
| February 2005 |
Stage 6 (Pathaway/The Gallery/Cornerstone) completed |
| June 2005 |
Champions Course construction commences |
| November 2005 |
Recycled water connected |
| February 2006 |
Health Club construction commences |
| March 2006 |
PGA House (National PGA Headquarters) construction commences |
| March 2007 |
Health Club completion |
| April 2007 |
PGA House (National PGA Headquarters) completion |